Teardown Chronicle

Day 35

New waterfront home  Sharon is away, but the project continues.

Spoken by Sharon Simms | Discussion: No Comments »

Teardown Chronicle - Day 30 (43)

2nd floorTeardown Chronicle - Day 30 (43). From the rainy street it didn’t look like much framing had been done today, but it looks as if the next floor joists/trusses have been delivered and are ready for the next stage.

Spoken by Sharon Simms | Discussion: No Comments »

Teardown Chronicle - Day 29 (42)

Framing nearly done on 2nd level Teardown Chronicle - Day 29 (42) Most of the second floor framing is done.

Spoken by Sharon Simms | Discussion: No Comments »

Teardown Chronicle - Day 28 (41)

2nd floor framing 2nd floor framing August 11, 2008.  Day 28 (41). Framing on 2nd floor.

Spoken by Sharon Simms | Discussion: No Comments »

Teardown Chronicle - Day 32 (45) - Second Level

Framing second levelIn the last week the floor trusses were completed, the plywood decking was attached, and framing has begun on the second level. You can already tell that this home won’t be a plain box.

Spoken by Sharon Simms | Discussion: No Comments »

Teardown Chronicle - Day 27 (38)

Floor trusses underway

Today many of the floor trusses that were delivered yesterday were installed.

Spoken by Sharon Simms | Discussion: No Comments »

Teardown Chronicle - Day 26 (37)

Floor trusses delivered Teardown Chronicle - Day 26 (37)  The floor trusses were delivered today as well as some plywood.

Spoken by Sharon Simms | Discussion: No Comments »

Teardown Chronicle - Day 22 (31)

Logo branded on masonryAs we wait for the floor joists to be delivered, the builder has put his Arthur Rutenburg logo on the front masonry wall. Note the plywood pieces over the places to be inspected after the concrete blocks are filled.

Spoken by Sharon Simms | Discussion: No Comments »

Teardown Chronicle - Day 19 (28)

Block walls completed Teardown Chronicle - Day 19 (28) Block walls have been completed.

Spoken by Sharon Simms | Discussion: No Comments »

Teardown Chronicle - Day 18 (27)

Block walls taking shapeTeardown Chronicle - Day 18 (27).  The masons have been very busy and you can now see the shape of the building.

Spoken by Sharon Simms | Discussion: No Comments »

« Previous Entries

Add to Technorati Favorites Directory of Real Estate Blogs Real Estate Blogs - Blog Top Sites

Copyright © 2007 Florida Real Estate Blog by Sharon Simms     Agent Login     Design by Real Estate Tomato     Powered by Tomato Blogs